In addition to the federation lifecycle alignment analysed in this annex (Mff ↔ EWBI), further work is required to assess and integrate selected **GSMA Operator Platform Northbound Interface (NBI)** APIs within the ENC platform.
### A.7.1 Introduction
The following NBI functional areas are identified as **ToDo items** for subsequent phases of analysis and implementation:
This clause defines the technical procedure for integrating **Federation Management** and the **GSMA Operator Platform Northbound Interface (NBI)** into the ENC platform.
-**AvailabilityZoneInfoSynchronization**
Management and synchronization of partner Operator Platform (OP) availability zones and related status updates.
Future work shall evaluate alignment with MEC system/resource discovery models and federation-aware exposure of availability information.
The implementation depends on the architectural option selected in Clause A.4:
-**ArtefactManagement**
Upload, removal, and retrieval of application descriptors, charts, and packages over E/WBI toward a partner OP.
Future analysis shall assess compatibility with ETSI GS MEC 010-2 application package management and the MEC 037 package structure, including the potential need for an adapter layer.
* Option 1 – MEC FM-Centric Native Implementation
* Option 2 – Transformation Function Integration
* Option 3 – Software-First Integration
-**ApplicationOnboardingManagement**
Registration, retrieval, update, and removal of applications toward a partner OP.
Alignment with MEC federation onboarding procedures and CAMARA Edge Application Management APIs shall be evaluated.
The procedure below outlines the required milestones and technical components. Detailed API harmonization and implementation tasks shall be performed according to the selected option.
-**ApplicationDeploymentManagement**
Creation, update, retrieval, and termination of application instances over E/WBI toward a partner OP.
Federation-aware lifecycle management, cross-domain orchestration, and instance state synchronization require further analysis.
At this stage, the integration of the GSMA NBI APIs is considered outside the scope of the present feasibility assessment and remains subject to: